Monday, July 25, 2011

Lead & Coal Update: Two Way Traffic Switches to Coal

LEAD & COAL IMPROVEMENTS PROJECT MARKS MAJOR MILESTONE:

COAL TO OPEN TO TWO-WAY TRAFFIC BETWEEN UNIVERSITY & I-25; LEAD TO CLOSE TO THRU TRAFFIC

IN SAME AREA EVENING OF SUNDAY, JULY 31, 2011

Construction Complete on Coal; Project Is One Month Ahead of Schedule at This Time; On Track for Completion in Spring 2012

Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets.

NOTE: All work is weather permitting and is subject to change without notice

At 8 p.m. on Sunday night, July 31, 2011, Coal will open to two-way traffic and Lead will close to thru traffic between University and Washington as crews mark an important project milestone – completion of construction on Coal. At this time, construction is one month ahead of schedule. During construction on Lead, Coal Avenue will have one lane of traffic in each direction.


Motorists will be able to turn left at five intersections with working traffic signals: 1) Coal at University; 2) Coal at Yale; 3) Coal at Girard; 4) Coal at Carlisle; and 5) Coal at Washington. Two crews will work on the project. One crew has been at work on Lead between I-25 and University since May 2011 and will complete that section sometime this fall. A second crew will begin at University and head east on Lead. Regular work hours will be Mon-Fri 7:30 a.m. - 4 p.m., although crews may work longer hours or on weekends as needed. Construction will include removing roadway, installing larger storm drainage pipeline, restoring roadway and installing new curb and gutter, sidewalks and landscaping. Motorists should allow extra time to reach their destinations, exercise caution in the construction zone, pay attention to construction signage and use an alternative route if possible. NO on-street parking will be allowed on Coal or Lead in the construction zone. Construction on Lead is expected to last through spring 2012.

Questions? Contact: Patti Watson, 245-3134, 269-9691 or pattiw@cooneywatson.com, Eric Martinez, 245-3138, 850-0163 or ericm@cooneywatson.com,Savina Garcia, 348-4018, 270-0682 or sgarcia@wilsonco.com, Patrick Shaw, 353-7370, or patricks@auiinc.net; Diane Sholtis, 768-3838 or dsholtis@cabq.gov. For more information, visit www.leadandcoal.com.

Thursday, July 7, 2011

Lead and Coal Construction Update

LEAD & COAL IMPROVEMENTS PROJECT
LOOKING AHEAD: CONSTRUCTION UPDATE
FOR WEEKS OF JULY 5-8, JULY 11-15, AND JULY 18-22, 2011
Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets and improving storm drainage.
NOTE: All work is weather permitting and is subject to change without notice

IMPORTANT NOTICE: If construction is going on in your neighborhood, there may be brief water or gas outages while crews relocate lines or make adjustments as needed. If there is a planned water or gas shutoff that will affect you, construction crews will place a notice on your front door and will try to contact you by knocking on your front door. They will let you know when the outage is scheduled and how long it is expected to last.

Coal Avenue from Girard to Carlisle
July 6, July 8 & 9 – Install block wall fencing
July 5-8 – Install landscaping
July 11-15 – Install landscaping

Coal Avenue from Carlisle to Washington
July 6, July 8 & 9 – Install block wall fencing
July 5-8 – Install landscaping
July 11-15 – install landscaping
July 18-22 – Install landscaping

Valley Gutter Tie-In Work on Coal
NOTE: Valley gutter tie-In work is being scheduled at specific intersections along Coal Avenue SE for the next three weeks. When valley gutter tie-ins are installed, access will not be permitted through the intersection for three days. Motorists are advised to use an alternate route.

July 5-8 – Valley gutter tie-ins are scheduled at Coal at Harvard, Coal at Cornell, Coal at Stanford, Coal at Columbia, Coal at Princeton, Coal at Vassar, Coal at Dartmouth and Coal at Richmond.

July 11-15 – Valley gutter tie-ins are scheduled at Coal at Wellesley, Coal at Bryn Mawr, Coal at Tulane, Coal at Amherst, Coal at Hermosa, Coal at Solano, Coal at Aliso, Coal at Morningside and Coal at Valverde.

Week of July 18-22 – Valley gutter tie-in is scheduled at Coal and Valverde and Coal at Graceland.

Installation of Ramps, Sidewalks and Headers
July 5-8 -- Ramps, sidewalks and headers are scheduled to be installed at specific addresses, including
402 Hermosa, 401-402 Aliso, 324 Morningside, 400 Sierra and 400 Montclaire

Eastbound Coal from Washington to Adams
July 11-15 – Remove asphalt, prepare sub grade and base course on roadway

July 18-22 – Prepare sub grade and base course on roadway, install conduit for lighting and traffic signal, install curb and gutter and repave median area, install fine grade base course on roadway

WORK ON LEAD AVENUE

Lead Avenue from Oak to Mulberry:
July 5-8 – Replace water services, install curb and gutter, prepare sub grade and install base course on roadway, install sleeving and conduit for electrical lines, install fire hydrant (Lead at Oak)
July 11-15 – Replace water services, install valley gutter fillets, install drive pads*, install sleeving and conduit for electrical lines
July 18-22 – Replace water services, install sleeving and conduit for electrical lines

Lead Avenue from Mulberry to Cedar:
July 5-8 – Replace water services, install lateral storm drainage lines, install curb and gutter, prepare sub grade and install base course on roadway, install sleeving and conduit for electrical lines, relocate water lines (Lead at Mulberry)
July 11-15 – Replace water services, install lateral storm drainage lines, install valley gutter fillets, install drive pads*, install sleeving and conduit for electrical lines
July 18-22 – Replace water services, install lateral storm drainage lines, install sleeving and conduit for electrical lines

Lead Avenue from Cedar to Spruce to Sycamore
July 5-8 – Replace water services, install lateral storm drainage lines, prepare sub grade and install base course on roadway, install sleeving and conduit for electrical lines, relocate water lines
July 11-15 – Replace water services, install lateral storm drainage lines, prepare subgrade and install base course on roadway, install sleeving and conduit for electrical lines, relocate water lines
July 18-22 – Install ramps, sidewalks and headers, install lateral storm drainage lines, replace water services, install valley gutter fillets, install drive pads*, install curb and gutter, install sleeving and conduit for electrical lines

Lead Avenue from Sycamore to Maple to Ash to University
July 5-8 -- Replace water services, install lateral storm drainage lines, install sleeving and conduit for electrical lines
July 11-15 -- Replace water services, install storm drainage pipelines and lateral lines, install sleeving and conduit for electrical lines, relocate water line (Lead at Maple)
July 18-22 – Replace water services, install lateral storm drainage lines, prepare sub grade and install base course on roadway, install sleeving and conduit for electrical lines

*When drive pads are installed, residents may not be able to park in their driveways for 3 days in order for the concrete to cure. The contractor will notify you via flyer when your drive pad is being re-poured.

General Information:
Construction is expected to last through spring 2012. Two (2) crews will be working on the project at the same time. Regular work hours will be 7 a.m.-4 p.m. Monday-Friday although crews may work later hours or on weekends if needed due to an emergency or unforeseen circumstance.

Wednesday, May 4, 2011

Lead & Coal Improvements Update

LEAD & COAL IMPROVEMENTS PROJECT LOOKING AHEAD: CONSTRUCTION UPDATE FOR WEEKS OF MAY 2-6, MAY 9-13 AND MAY 16-20, 2011


Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets and improving storm drainage.
NOTE: All work is weather permitting and is subject to change without notice

(Work is shown on Coal heading eastward)

IMPORTANT NOTICE: If construction is going on in your neighborhood, there may be brief water or gas outages while crews relocate lines or make adjustments as needed. If there is a planned water or gas shutoff that will affect you, construction crews will place a notice on your front door and will try to contact you by knocking on your front door. They will let you know when the outage is scheduled and how long it is expected to last.

TRAFFIC SWITCH AS OF MAY 1, 2011:
Beginning Sunday, May 1, 2011, Coal Avenue will open to two-way traffic from I-25 to University Blvd. and Lead Avenue will close to thru traffic between I-25 and University Blvd. (Local traffic will be allowed on Lead between I-25 and University.) The designated bike detour will also change. Details are on http://www.leadandcoal.com/.

IMPORTANT NOTICE: GIRARD TO BE CLOSED AT COAL FROM MAY 8-22, 2011:
Beginning Sunday, May 8, 2011, Girard Blvd. SE will be closed in the area of Girard and Coal Ave. SE for approximately 14 days for crews to replace the roadway. More details will be provided soon via a separate information flier.

Coal Avenue from Yale to Harvard to Cornell to Stanford to Columbia:
May 2-6 – Install landscaping, install fencing
May 9-13 – Install landscaping
May 16-20 – Install landscaping

Coal Avenue from Columbia to Princeton to Vassar to Girard:
May 2-6 – Install landscaping, install fencing, install ramps, sidewalks and headers
May 9-13 – Install landscaping
May 16-20 – Install landscaping

Coal Avenue from Girard to Dartmouth to Richmond:
May 2-6 – Install fencing, install inlets for storm drainage, install ramps, sidewalks and headers
May 9-13 – Install ramps, sidewalks and headers

Coal Avenue from Richmond to Wellesley:
May 2-6 – Install fencing
May 9-13 – Install inlets for storm drainage, install ramps, sidewalks and headers
May 16-20 – Install ramps, sidewalks and headers

Coal Avenue from Wellesley to Tulane to Amherst to Carlisle:
May 2-6 – Install fencing, install drive pads* and alleys, install valley gutter fillets to direct water away from road and across intersection, install curb and gutter, prepare sub grade on roadway and install base course
May 9-13 – Install ramps, sidewalks and headers; install drive pads* and alleys, install valley gutter fillets to direct water away from road and across intersection, pave turnouts
May 16-20 – Install inlets for storm drainage, install ramps, sidewalks and headers, install fine grade base course on roadway, repave roadway

Coal Avenue from Carlisle to Hermosa to Solano
May 2-6 – Install valley gutter fillets to direct water away from road and across intersection
May 9-13 – Install valley gutter fillets to direct water away from road and across intersection, install curb and gutter, pre sub grade on roadway and install base course
May 16-20 – Install inlets for storm drainage, prepare sub grade on roadway and install base course, install fine grade base course on roadway

Coal Avenue from Solano to Aliso to Morningside to Montclaire to Sierra
May 2-6 – Install drive pads* and alleys, install valley gutter fillets to direct water away from road and across intersection
May 9-13 – Install fine grade base course on roadway, prepare sub grade on roadway and install base course, repave roadway
May 16-20 – Install inlets for storm drainage, install drive pads* and alleys, install valley gutter fillets to direct water away from road and across intersections, install curb and gutter, prepare sub grade on roadway and install base course

Coal Avenue from Sierra to Washington
May 2-6 – Prepare sub grade and base course on roadway
May 9-13 – Prepare sub grade and base course on roadway, install curb and gutter
May 16-20 – Prepare sub grade on roadway and install base course

Finishing Work in Area of Carlisle/Garfield
While Carlisle did reopen last week, crews will complete some finishing work on Carlisle from north of Coal to the intersection of Garfield and Coal during the week of May 2-6, 2011. Work will include pouring two additional inlets for storm drainage, pouring a retaining wall footer, a wheelchair ramp and replacing curb.

Lead Avenue from Oak to Cedar
May 2-6 – Remove asphalt paving

Lead Avenue from Cedar to Sycamore
May 9-13 – Remove asphalt paving

Lead Avenue from Mulberry to Spruce
May 16-20 – Locate underground utilities and install storm drainage infrastructure

*When drive pads are installed, residents may not be able to park in their driveways for 3 days in order for the concrete to cure. The contractor will notify you via flyer when your drive pad is being re-poured.

General Information:
Construction is expected to through spring 2012. Two (2) crews will be working on the project at the same time. Regular work hours will be 7 a.m.-5 p.m. Monday-Friday although crews may work later hours or on weekends if needed due to an emergency or unforeseen circumstance.

Monday, March 21, 2011

CARLISLE TO BE CLOSED FROM NORTH OF COAL TO GARFIELD

Beginning at 8 p.m. on Sunday, March 27, 2011 and lasting for approximately 30-45 days (through approximately April 27-May 12, 2011) Carlisle Boulevard SE will be closed from north of Coal Avenue SE to south to Garfield Avenue SE in order for crews to install large storm drainage infrastructure in Carlisle.

This work will be done in two phases:

PHASE 1: Carlisle will be closed from south of Lead to north of Garfield. This phase is scheduled from approximately March 27-April 11, 2011. Garfield will remain open during this phase, but all commuters and non-local residents should use Girard Blvd. SE and Lead Avenue SE as detours.

PHASE 2: The intersection of Garfield and Carlisle will be closed from approximately April 12, 2011 until April 27, 2011 or until work is complete.

Crews will be working extended hours Monday-Friday, from approximately
7 a.m.-5 p.m. Monday-Friday. Additional evening or weekend hours may be required due to unforeseen circumstances.

ACCESS WILL BE MAINTAINED TO ALL LOCAL RESIDENCES AND BUSINESSES.

Motorists are asked to use an alternate route if possible, allow extra time to reach their destinations, exercise caution in the construction zone, and follow all signs.

QUESTIONS? Contact:
Patti Watson, 245-3134, 269-9691 or pattiw@cooneywatson.com
Eric Martinez, 245-3138, 850-0163 or ericm@cooneywatson.com
Savina Garcia, 348-4018 or 270-0682 or sgarcia@wilsonco.com
Diane Sholtis, 768-3838 or dsholtis@cabq.gov

For more information, visit http://www.leadandcoal.com/





BUS DETOUR MAP DURING CLOSURE OF CARLISLE


During the planned closure of Carlisle from north of Coal to Garfield, beginning March 28, 2011, Bus Route 16/18 “The Bug” will have a special detour:
Southbound busses:
Will head south on Carlisle, then east on Lead, then south on Hermosa, then west on Ridgecrest/Burton, the south on Carlisle.
Northbound busses:
Will head north on Carlisle, then west on Burton, then north on Amherst, then east on Lead, then north on Carlisle.
Temporary bus stops will be located just north of Garfield and just south of Lead on Amherst and on Hermosa. Regular bus stops located along Carlisle at Ridgecrest, between Garfield and Coal and south of Lead will be closed while construction is taking place on Carlisle.
These detours and temporary bus stops are expected to be in place through the closure of Carlisle, scheduled to last approximately 30-45 days (through April 27-May 12, 2011). For more information, please contact the City of Albuquerque Transit Department at www.cabq.gov/transit or call 243-7433.

Wednesday, February 16, 2011

Lead and Coal Construction Update

AS PART OF LEAD AND COAL IMPROVEMENTS PROJECT, CREWS TO CLOSE ONE LANE OF NORTHBOUND CARLISLE FROM SOUTH OF GARFIELD TO NORTH OF COAL FOR LOCATION OF UNDERGROUND UTILITIES FEBRUARY 16 AND 17, 2011

Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets and improving storm drainage.
NOTE: All work is weather permitting and is subject to change without notice

As part of construction for the Lead and Coal Improvements Project, crews will close one lane of northbound Carlisle from south of Garfield to north of Coal Avenue in order to locate underground utilities on Wednesday, Feb. 16 and Thursday, Feb. 17, 2011.
(See map).

During this closure one lane of northbound traffic and one lane of southbound traffic will be open on Carlisle in the construction zone.

Regular work hours will be 7:30 a.m.-5 p.m...

ACCESS WILL BE MAINTAINED TO ALL LOCAL BUSINESSES AND RESIDENCES.

MOTORISTS ARE ASKED TO ALLOW EXTRA TIME TO REACH THEIR DESTINATIONS, EXERCISE CAUTION IN THE CONSTRUCTION ZONE, AND FOLLOW ALL SIGNS.

QUESTIONS? Contact:
Patti Watson, 245-3134, 269-9691 or pattiw@cooneywatson.com.
Eric Martinez, 245-3138, 850-0163 or ericm@cooneywatson.com.
Savina Garcia, 348-4018 or 270-0682 sgarcia@wilsonco.com.
Patrick Shaw, 242-4848, x3015 or patricks@auiinc.net
Diane Sholtis, 768-3838 or dsholtis@cabq.gov


For more information, visit: www.leadandcoal.com.

Tuesday, January 18, 2011

Upcoming Lead and Coal Construction

LEAD & COAL IMPROVEMENTS PROJECT
LOOKING AHEAD: CONSTRUCTION UPDATE
FOR WEEKS OF JANUARY 17-21, 2011,
JANUARY 24-28, 2011 AND JANUARY 31-FEBRUARY 4, 2011

Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets and improving storm drainage.
NOTE: All work is weather permitting and is subject to change without notice
Coal Avenue from Mulberry to Sycamore:
Jan. 24-28 – Repave roadway*

Coal Avenue from Oak to Sycamore:
Jan. 17-21 – Install conduit for intelligent traffic system (ITS) and lighting, install driveways and sleeves, install fine grade base course on roadway

Coal Avenue from Sycamore to Hazeldine:
Jan. 24-28 – Repave roadway*

Coal Avenue from Sycamore to Ash:
Jan. 17-21 – Install valley gutter to direct water away from road and across intersections, install driveways and sleeves
Jan. 24-28 – Install conduit for intelligent traffic system (ITS) and lighting, install driveways and sleeves, install fine grade base course on roadway
Jan. 31- Feb. 4 – Install fine grade base course on roadway

Coal Avenue from Sycamore to Coal Place:
Jan. 17-21 – Install inlets for storm drainage
Jan. 24-28 – Install inlets for storm drainage

Coal Avenue from University to Yale:
Jan. 17-21 – Install curb and gutter, prepare sub grade and base course for curb and gutter
Jan. 24-28 – Install curb and gutter, install inlets for storm drainage, install valley gutter to direct water away from road and across intersections

Coal Avenue from Yale to Harvard:
Jan. 17-21 – Install sleeves and prepare intersection crossings, prepare sub grade and base course for curb and gutter
Jan. 24-28 – Prepare sub grade and base course for curb and gutter, install curb and gutter
Jan. 31-Feb. 4 – Install curb and gutter

Coal Avenue from Harvard to Cornell to Stanford;
Jan. 17-21 – Install storm drainage trunk line and lateral lines
Jan. 24-28 – Prepare sub grade and base course for curb and gutter
Jan. 31-Feb. 4 – Install inlets for storm drainage, prepare sub grade and base course for curb and gutter, install curb and gutter

Coal Avenue from Stanford to Columbia to Princeton:
Jan. 17-21 – Install storm drainage trunk line
Jan. 24-28 – Install storm drainage trunk line and lateral lines
Jan. 31-Feb. 4 – Prepare sub grade and base course for curb and gutter, install sleeves and prepare crossings

Coal Avenue from Princeton to Vassar:
Jan. 17-21 – Relocate water lines
Jan. 24-28 – Install storm drainage trunk line and lateral lines

Coal Avenue from Vassar to Girard:
Jan. 17-21 – Relocate water lines
Jan. 24-28 -- Remove asphalt paving on roadway
Jan. 31-Feb. 4 – Install storm drainage trunk line and lateral lines

Coal Avenue from Girard to Dartmoth:
Jan. 24-28 – Remove asphalt paving on roadway, relocate water lines
Jan. 31-Feb. 4 – Install storm drainage trunk line and lateral lines

Coal Avenue from Dartmouth to Richmond:
Jan. 24-28 -- Remove asphalt paving from roadway, relocate water lines, install storm drainage lateral lines

Coal Avenue from Richmond to Bryn Mawr to Wellesley:
Jan. 24-28 -- Remove asphalt paving from roadway

Coal Avenue from Wellesley to Tulane to Amherst:
Jan. 31-Feb. 4 – Remove asphalt paving from roadway

Coal Avenue at Montclaire:
Jan. 17-21 -- Relocate gas lines

* Repaving is dependent on daytime temperature of 40-50 degrees Fahrenheit or warmer for several hours.

General Information:
Construction is expected to last approximately 18 months, through spring 2012. The contractor will work in approximate 5-block areas, finishing all construction in one area before moving on to the next. 2 crews will be working on the project at the same time. Initial work zones will be at Coal & I-25, heading east and at Coal & University, heading east. Regular work hours will be daylight hours (7 a.m.-5 p.m. Monday-Friday) although crews may work later hours or on weekends if needed due to an emergency or unforeseen circumstance.

Friday, November 5, 2010

CONSTRUCTION BEGINS MONDAY, NOVEMBER 8th, 2010 ON LEAD AND COAL IMPROVEMENTS


Creating beautifully landscaped, environmentally sensitive, neighborhood, bicycle and pedestrian friendly streets.
NOTE: All work is weather permitting and is subject to change without notice

Construction begins Monday, Nov. 8 in Work Zone 1 (see map below). During construction, Coal Ave. SE will be closed to thru traffic from I-25 to Washington Street, with only local traffic allowed. Thru traffic will be shifted to Lead Ave. with one lane of traffic in each direction. FOR SAFETY REASONS AND TO KEEP TRAFFIC FLOWING ON LEAD, traffic will only be able to turn left at four intersections with working traffic signals: 1) Lead at University; 2) Lead at Yale; 3) Lead at Girard; and 4) Lead at Carlisle. Two crews will begin work at Coal and I-25 and at Coal and University. Regular work hours will be Monday-Friday 7:30 a.m.-5 p.m., although crews may work longer hours or on weekends as needed. Construction in Work Zone 1 is expected to last through late March or early April 2011. Crews will remove roadway, install a larger storm drainage pipe, restore roadway and install new curb and gutter, sidewalks and landscaping.

Motorists should allow extra time to reach their destinations, exercise caution in the construction zone, pay attention to construction signage and use an alternative route if possible.
NO on-street parking will be allowed on Lead or Coal in the construction zone.

Questions? Contact: Patti Watson, 245-3134, 269-9691 or pattiw@cooneywatson.com, Eric Martinez, 245-3138, 850-0163 or ericm@cooneywatson.com,
Savina Garcia, 348-4018, 270-0682 or sgarcia@wilsonco.com, Patrick Shaw, 242-4848, x3015, 353-7370, or patricks@auiinc.net; Diane Sholtis, 768-3838 or dsholtis@cabq.gov
For more information, visit www.leadandcoal.com

Tuesday, October 5, 2010

Lead and Coal Construction Meeting

CITY OF ALBUQUERQUE
DEPARTMENT OF MUNICIPAL DEVELOPMENT
PUBLIC INFORMATION MEETING
LEAD AND COAL IMPROVEMENTS
From I-25 to Washington Street

The City of Albuquerque will be reconstructing Lead and Coal Avenues between I-25 and Washington Street. The project includes intersection improvements, storm drainage infrastructure, traffic calming elements, bicycle lanes, sidewalk and landscaping improvements. These improvements are taking place based on the New Vision for Lead and Coal study. The project is expected to last until the spring of 2012.

This meeting is an opportunity for the public to ask questions about the upcoming construction, view construction detour plans, receive helpful information about the project and meet the construction team.

Public Meeting
Wednesday, October 13, 2010
Open House:
11:00 AM to 1:00 PM and
3:00 PM to 6:00 PM
Informational Presentation:
6:00 PM

Immanuel Presbyterian Church
Fellowship Hall
114 Carlisle Blvd. SE
Albuquerque, NM 87108

Please enter Fellowship Hall through the door on Carlisle.

ADA: To request Americans with Disabilities Act (ADA)-related accommodations for this meeting, contact Diane Sholtis at (505) 768-3838.